Kuala Lumpur PIPE ROOF PROJECT
Kuala Lumpur, the capital of Malaysia, is famous for the Petronas Twin Towers,
which boasts a height of 451m. As the city continues to develop day by day, it is in an urgent need to further improve the transportation network.
The KVMRT (Klang Valley Mass Rapid Transit), which connects the east and west of the metropolitan area, is under construction.
The plan is to cross several aortas of the transportation network, and the pipe roof
method with Unclemole Super has been adopted for the underground crossing of the Kuala Lumpur Seremban Expressway, and it is currently under excavation. Since it is a big project, we have daily inspections and safety inspections, and we are aiming for the
early completion of the construction with a close attention.
Reception Shaft
CONSTRUCTION SUMMARY
Construction Site: Kuala Lumpur, Malaysia
Pipe Type: Steel pipe φ800mm×9m
Pipe Roof Length: 60m×23no.×2places
Total Length: 2760m
Soil Condition: Sandy Gravel
Minimum earth cover depth: 4m
Construction site
UNCLEMOLE SUPER
Outer diameter:812mm
Machine Length: 3020mm
Weight:3800kg
Crusher type: Cone crusher
MACHINE SPECIFICATION
Unclemole Super
Overview of the PIPE ROOF Project
Arrival Shaft
Plan view of the construction site
9m steel pipe installation for jacking equipment
9m steel pipe jacking
Cross section of the PIPE ROOF
Installed Unclemole on the construction site
Unclemole Super is about to start jacking
After the completion of a pipe jacking